SCS Fails to File Appeal in SD and the IUC Final Decision and Order, Dated 25 June, 2024 – Phase One – HLP-2021-0001

starting with pages 476….

V. ORDERING CLAUSES

IT IS THEREFORE ORDERED:

1. The petition for hazardous liquid pipeline permit filed by Summit Carbon Solutions, LLC, on January 28, 2022, as subsequently revised, is granted subject to the terms and conditions of this order.

2. Motions and objections not previously granted or sustained are overruled. Arguments presented in written filings or made orally at the hearing that are not addressed specifically in this final decision and order are rejected, either as not supported by the evidence or as not being of sufficient persuasiveness to warrant detailed discussion.

3. Summit Carbon Solutions, LLC, shall continuously revise Exhibit E as it obtains consents, permits, authorizations, or as consultations occur resulting in Summit Carbon Solutions, LLC, either receiving a consent, permit, or authorization, or a determination that a consent, permit, or authorization is not needed after consulting with a particular entity.

4. Summit Carbon Solutions, LLC, shall continuously revise the Federal and State Permit Tracker in Exhibit F as it obtains consents, permits, authorizations, or as consultations occur resulting in Summit Carbon Solutions, LLC, either receiving a consent, permit, or authorization, or a determination that a consent, permit, or authorization is not needed after consulting with a particular entity.

5. Summit Carbon Solutions, LLC, shall not commence construction on any segment of pipe in Iowa until it has obtained agency approval for a route and sequestration site in North Dakota and an agency approval of a route in South Dakota, except as described in Ordering Clauses 6 and 7.

6. Summit Carbon Solutions, LLC, shall not commence construction of Trunk Line 3, north of the Superior Ethanol Plant, or Lateral Line 2, until it has received agency approval from Minnesota for a connection to ethanol plants located in Minnesota as well as compliance with Ordering Clause 5.

7. Summit Carbon Solutions, LLC, shall not commence construction of Trunk Line 5, south of Plymouth Energy, until it has an approved route in Nebraska to at least one ethanol plant in addition to compliance with Ordering Clause 5. …..

and more….

Page 477 of the Final Decision and Order

Page 477

 

Page 481

 

SD Deny!

https://southdakotasearchlight.com/2025/04/22/south-dakota-regulators-deny-carbon-pipeline-permit-again-summit-carbon-solutions-vows-reapply/

SUMMIT FAILS TO FILE AN APPEAL TO SOUTH DAKOTA PUC DECISION

South Dakota HP24-001 SCS Docket Closed 5/27/25 = https://puc.sd.gov/Dockets/HydrocarbonPipeline/2024/HP24-001.aspx
Download File: https://freesoilfoundation.com/wp-content/uploads/2025/06/SD-Docket-HP24-001.pdf

https://freesoilfoundation.com/summit-fails-to-file-an-appeal-to-south-dakota-puc-decision/

See IUC Filing:  https://freesoilfoundation.com/wp-content/uploads/2025/06/HLP-2021-0001_Order_2024.06.25_2147516_240625-143412.pdf